Colman Engineering, PLC | Civil, Environmental, and Water Resources Engineering Services

  • Home
  • Services
    • Land Development
    • Water Resources
    • Environmental
  • Portfolio
  • About
  • Contact
  • Blog
  • Jobs
  • Home
  • Services
    • Land Development
    • Water Resources
    • Environmental
  • Portfolio
  • About
  • Contact
  • Blog
  • Jobs

Blog

Discussing current issues in engineering

Boulders Slowing Progress on the Chesapeake Bay Bridge Tunnel Expansion Project Now 2 Years Behind Schedule

10/6/2020

 
Picture
Photo credit: Jim Powers from Chester Springs, PA, USA, CC BY 2.0
Originally slated to be completed in 2022, the construction of a second Chesapeake Bay Bridge Tunnel in Virginia Beach is now officially two years behind schedule with the newest hinderance to timely construction being large granite boulders.

The tunnel expansion project is designed to add two additional tunnels parallel to the two current tunnels in order to end the two-way traffic congestion inside the existing tunnels. Construction of the first new tunnel started in 2017 and is being built under a shipping channel located nearest to Virginia Beach. The project was originally scheduled to be completed in 2022 with a price tag of $756 million. However, after a number of delays, the current projected completion date is 2024 with giant boulders being the newest obstacle.

The granite boulders, as large as 6 feet in diameter and weighing up to 25 tons, help make up two 5.25 acre manmade islands. In order to construct the new 5,700 ft long tunnel, the boulders need to be excavated in order to provide access for a tunnel boring machine (TBM) arriving from Germany this year. The TBM is designed to bore through soft soil, not hard granite boulders. Therefore, the construction contractors must pound steel pilings through the boulders as part of the excavation effort to provide access for the TBM. Mike Crist, the bridge tunnel’s deputy executive director of infrastructure described this process as driving a nail through granite rock.

As a result, construction progress is going much slower than anticipated due to the new boulder debacle and construction on the second parallel tunnel is not expected to begin before 2037. You can find more info on the Chesapeake Bay Bridge Tunnel project and the tunnel boring process here.

Comments are closed.

    Colman Engineering, PLC

    A professional engineering firm located in Harrisonburg, VA

    Archives

    January 2022
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    January 2018
    April 2015
    March 2015
    January 2015

    RSS Feed

Picture
Colman Engineering, PLC
1123 S. High Street
Harrisonburg, VA 22801
contact@colmanengineering.com
(540) 246-3712
Colman Engineering, PLC

© Colman Engineering, PLC  |  All Rights Reserved